Quick start
1/4: Check your order
- Please check the order against the
delivery slip to ensure it is complete.
The components illustrated below are required for commissioning and operating the Jellox Node . However, the sets may also contain other components.
1 MDN Magnet 2 Jellox Node 3 Antenna (e.g.Flat antenna Disc Multi Band FME-F 2m )
2/4: Create a site
|
|
If you do not have an account yet, you will receive the web address of the server, the access data and any credit balance from your responsible sales partner. |
- Log in to the server via the web
interface.
- Click on "Customer". Select an existing
customer or create a new one.
Only if you have an account to manage multiple customers.
1 Menu item to call up the list of customers 3 List of available customers 2 Creating a new customer - Click on "Sites / Applications". Open the
wizard for creating a new site by clicking on the plus symbol (2).
1 Menu item to call up the list of existing sites / applications 2 "Add new site / application" symbol - Follow the wizard
instructions through to the "Done" step.
The serial number required for the Wizard can be found on the type plate of the device.
- Review the details in the summary
and create the site by clicking the "Create site" button.
By clicking "create site", the site that is subject to fees will be created.
1 This amount is debited from the customer's account for this site immediately upon creation and subsequently on a monthly basis. 2 Checkbox to accept the general terms and conditions 3 Link to the general terms and conditions 4 "Create site" button - Review the created site.
1 Name of the site. Click on the name to open the specific input screen for configuring the site. 2 Product name as specified on the type plate of the device 3 Serial number of the device linked to the site 4 State of the site
3/4: Install remote sensor module
|
|
The installation of the remote sensor modules varies depending on the module type. |
- Install the remote sensor modules of type LVL‑R‑5 (if included)
For optimum accuracy, install the LVL‑R‑5
- at a location with calm water surface
- centrally above the flume
- in distance from structures and fittings such as ladders or struts
- perpendicular to the water surface
- at a min. distance of 30 cm to the water surface.
A detailed explanation of the installation is provided here
- Install the remote sensor modules of type Gauge
(if included)
A detailed explanation of the installation is provided here
- Install the remote sensor modules of type VEL‑R‑5 (if included)
For optimum accuracy, install the VEL‑R‑5
- at a location with constant flow
- in the centre of a channel that runs straight for a long distance
- parallel to the flow
- against the direction of flow (upstream)
- at an angle of 45° to the water surface
- with the "top marking" facing upwards
A detailed explanation of the installation is provided here
4/4: Commissioning the Jellox Node
- Connect the antenna.
How-To-Video: Connecting the Multi band antenna with bracket

1 Antenna connector 2 Antenna cable - Click on the name of the site to open the
specific input screen for configuring the site.

1 Site name - Start the "Guided commissioning" process by clicking on the
corresponing button.

1 Opens the input screen for the guided commissioning process - The "Guided commissioning" wizard
first prompts you to establish a connection.
To do so, hold the MDN Magnet on the spot shown in the following illustration until the symbol on the display that indicates the status of the mobile nework connection starts blinking.
How-To-Video: Triggering a connection
1 MDN Magnet 2 Jellox Node 3 Status of the mobile network connection 4 detected hold of the reed switch A detailed explanation of the display is provided here
- Open the relevant
wizards to configure the individual components one by one and follow the instructions.
At last, open the "wizard to complete the set-up" (5).
Not every component needs to be configured immediately. You can also configure the device later via the individual input windows or you can restart the guided commissioning process.
1 Opens the wizard for the basic configuration of the measurement system 2 Opens the wizard to configure a remote sensor module of type LVL-R-5 3 Opens the wizard to configure a remote sensor module of type Gauge 4 Opens the wizard to complete the commissioning process
Congratulations!
You have successfully commissioned your Jellox Node !