"Guided commissioning" input screen
This input screen is opened by clicking on the icon with the three stars, which is located on the right-hand side of the title bar in the "Measurement System" configuration section of the site.
For the guided commissioning process an active connection between the Jellox Node and the myDatanet server is required. Therefore, you are first prompted to initiate a transfer by pressing the magnetic switch for at least 3 seconds (see Reed switch). After that, the list of components to be configured is displayed. Should an update be required for the firmware or the IoT application, this will be carried out immediately after the connection has been established. In this case, the input screen displays a corresponding message until the update is complete. Only then will the list of components that need to be configured be displayed. This list contains one entry for the measurement systemand one entry for each remote sensor module linked to a measurement channel.
Once the guided commissioning process has been initiated and the connection has been established, the Jellox Node will remain connected to the myDatanet server for 10 minutes. Once the timeout has expired or when the commissioning process is complete, the online connection between the Jellox Analog and the myDatanet server is terminated.
List of components to be configured
| 1 | Opens the wizard for the basic configuration of the measurement system |
| 2 | Opens the wizard to confiture a remote sensor module of type LVL-R-5 |
| 3 | Opens the wizard to configure a remote sensor module of type Gauge |
| 4 | Opens the wizard to complete the commissioning process |
Recommended procedure
- To configure the individual components, open the relevant wizards one by one.
- Follow the instructions in the wizards.
When clicking on "Next", the entries made in the current step are saved immediately.
- Open the wizard to complete the commissioning process.